What is Inclusive Housing under UDCPR?

In areas where UDCPR Regulation 3.8 is applicable, qualifying residential layouts and Group Housing projects of 4,000 sq.m. or more are subject to Inclusive Housing requirements for Economically Weaker Sections (EWS) and Low Income Groups (LIG), unless an exemption under Regulation 3.8.2 applies.

The concept is simple: when a developer builds a residential project on a qualifying plot of 4,000 sq.m. or more, they must set aside a portion of the built-up area for small, affordable flats (30–50 sq.m. carpet area) meant for lower-income families. These flats are then allotted through MHADA's lottery system — the developer does not get to sell them on the open market at market rates.

Think of it this way: if you are building 100 market-rate flats on a large plot, the government says you must also build a certain number of smaller, affordable flats alongside them. This ensures that new residential areas are not exclusively for the wealthy — they include housing for people who work in those areas but cannot afford market prices.

Key Takeaways — What You Need to Know

  • For qualifying Group Housing projects, Inclusive Housing = 20% of Basic FSI as EWS/LIG tenements.
  • The applicability threshold is 4,000 sq.m. of qualifying plot area (after prescribed deductions).
  • The 20% is calculated on Basic FSI only — not on Premium FSI, TDR, or other additional FSI.
  • Unit size: 30–50 sq.m. carpet area per tenement.
  • The Inclusive Housing FSI is over and above the normal permissible FSI — it does not eat into your project potential.
  • The October 2024 GR expanded applicability from Municipal Corporation areas to all Planning Authority areas in cities with 10 lakh+ population.
  • The August 2026 regulatory direction proposes shifting Inclusive Housing administration from MHADA to the concerned Planning Authority — verify the latest local authority circular before statutory submission.

Latest Update — August 2026

The latest reported regulatory direction proposes shifting the primary possession, management and allotment responsibility for Inclusive Housing from MHADA to the concerned Planning Authority. The core 20% requirement, 4,000 sq.m. threshold, 30–50 sq.m. unit-size provision and Basic-FSI calculation are not reported to have changed. This remains a proposed / pending regulatory transition until confirmed through the final Official Gazette / applicable local-authority circular.

📋

Primary reference: Unified Development Control and Promotion Regulations for Maharashtra State, Government of Maharashtra, Urban Development Department, 2 December 2020. Regulation 3.8 governs Inclusive Housing. Amendment 1: GR No. TPS-1824/1075/CR.87/2024/UD-13, dated 07.10.2024. Amendment 2 (August 2026): Proposed shift of administrative authority from MHADA to Planning Authority — pending final Gazette confirmation.

When Does the 4,000 sq.m. Rule Apply?

The Inclusive Housing obligation kicks in when you have a residential subdivision, layout, or Group Housing project on qualifying land of 4,000 sq.m. or more. This is the area after prescribed deductions such as DP/RP roads and reservations have been set aside.

But here is the important part — not every plot above 4,000 sq.m. automatically triggers the obligation. Regulation 3.8.2 contains a list of specific exemptions (we cover these in detail below). So the correct way to think about it is: "Does my plot meet the threshold and does it fall outside the exemptions?"

Who does it apply to?

Originally (under UDCPR as notified in 2020), Regulation 3.8.1 limited Inclusive Housing applicability to areas within Municipal Corporation limits. The October 2024 amendment changed this significantly — it now applies to all Planning Authority areas in cities and towns with a population of 10 lakh (1 million) or more.

⚠️

Common mistake: Do not assume that every residential plot above 4,000 sq.m. requires 20% EWS/LIG. Always check whether the project falls within an applicable area and whether any exemption under Regulation 3.8.2 applies. Oversimplifying this can lead to incorrect feasibility calculations.

The 20% Rule — How Inclusive Housing is Calculated

The calculation depends on whether you are doing a layout/subdivision or a Group Housing project. Both have the same 20% base, but they calculate it differently.

For Layout / Subdivision

In a layout or subdivision, the obligation is on land area: the developer must provide a minimum 20% of qualifying plot area for affordable plots or EWS/LIG provision. The options are:

  1. Provide developed EWS/LIG plots of 30–50 sq.m. each for direct allotment to eligible beneficiaries.
  2. Provide equivalent plot area (20% of qualifying plot) for construction of EWS/LIG tenements.
  3. Developer constructs EWS/LIG tenements on the 20% plot area under the Group Housing provisions.

For Group Housing

This is the more common scenario for urban projects, and the calculation is on built-up area: the developer must construct EWS/LIG tenements equal to at least 20% of the Basic FSI.

Inclusive Housing Calculation (Group Housing)
Inclusive Housing Area = 20% × (Plot Area × Basic FSI) Example: Plot area = 10,000 sq.m. Basic FSI = 1.10 Basic FSI area = 10,000 × 1.10 = 11,000 sq.m. IH requirement = 20% × 11,000 = 2,200 sq.m.
⚠️

Critical point: The 20% is on Basic FSI only. If your total project potential reaches 3.0 FSI through Premium FSI and TDR, you still calculate Inclusive Housing on the Basic FSI (e.g. 1.10), not on 3.0. The additional FSI components do not attract a separate Inclusive Housing obligation.

Worked Calculation Example

Let us walk through a real-world example so the maths is crystal clear.

Parameter Value Explanation
Gross plot area 12,000 sq.m. Total plot as per title / survey records
Area after deductions (DP road, reservations) 10,000 sq.m. Qualifying plot area after prescribed deductions
Basic FSI 1.10 As per applicable zone in UDCPR
Basic FSI built-up area 11,000 sq.m. 10,000 × 1.10 = 11,000 sq.m.
Inclusive Housing requirement (20%) 2,200 sq.m. 20% × 11,000 = 2,200 sq.m. of EWS/LIG tenements
Premium FSI (say 0.50) 5,000 sq.m. This does NOT increase IH obligation
TDR loaded (say 0.40) 4,000 sq.m. This does NOT increase IH obligation
Total project potential 22,200 sq.m. 11,000 (basic) + 5,000 (premium) + 4,000 (TDR) + 2,200 (IH FSI-exempt / over-and-above BUA)
The 2,200 sq.m. Inclusive Housing area is over and above the 20,000 sq.m. of permissible project FSI. It is FSI-exempt / over-and-above permissible FSI BUA under Regulation 3.8.2; the construction and compliance obligations still remain.

Notice the last point: the 2,200 sq.m. of Inclusive Housing does not consume your permissible FSI. It sits on top of your normal entitlements. This is an important feasibility point — the obligation to build affordable units comes with the benefit that those units do not reduce the market-rate area you can build.

EWS/LIG Unit Size: 30–50 sq.m. Carpet Area

Each Inclusive Housing tenement must be between 30 sq.m. and 50 sq.m. carpet area. Carpet area is the net usable floor area of the apartment, excluding external walls, service shafts, exclusive balcony/verandah areas and exclusive open-terrace areas, but including the area covered by internal partition walls.

This range is designed to serve EWS and LIG families — small enough to remain affordable, large enough to be liveable. The units cannot be amalgamated into larger flats, so the affordable housing stock is preserved as individual small dwellings.

FSI Treatment — Is It Over and Above Permissible FSI?

Yes. The Inclusive Housing built-up area is not counted toward your normal FSI. It is granted as additional FSI, over and above the permissible Basic FSI, Premium FSI, and TDR that the project is entitled to.

In our example above, the developer gets 11,000 sq.m. of Basic FSI + 5,000 sq.m. of Premium + 4,000 sq.m. of TDR = 20,000 sq.m. of market-rate potential, plus 2,200 sq.m. of Inclusive Housing FSI on top. The total buildable area is 22,200 sq.m., not 20,000 sq.m.

Under Regulation 3.8.2, the Affordable Housing built-up area is FSI-exempt / over and above the normal permissible FSI. The developer must nevertheless account for the construction, planning and compliance obligations associated with those units.

Options for Providing Inclusive Housing

The regulation does not force you to build the affordable units on the same plot in every case. There are options:

Option 1: Same plot (default)

The most common approach. The developer constructs EWS/LIG tenements on the same plot as the main project. The OC for the market-rate buildings is linked to the OC for the Inclusive Housing component — so the balance development cannot receive its Occupancy Certificate until the Affordable Housing component is also ready for the required OC.

Option 2: Alternate location within 1 km or same ward

Regulation 3.8.2 permits the affordable housing component to be provided at another location within 1 km of the original plot or within the same ward, subject to prescribed conditions. For Group Housing on an alternate plot, the regulation includes a 40% of basic permissible FSI receiving-plot mechanism with land-rate proportional adjustment.

Option 3: FSI / DR / TDR route

The regulation includes provisions for handing over affordable plots against FSI/DR and awarding TDR for unutilised additional FSI, subject to TDR regulations. This route is less common in practice but available for specific situations.

Practical tip

Most developers prefer to build the Inclusive Housing on the same plot because (a) it avoids the complexity of acquiring a separate alternate plot, (b) the Inclusive Housing BUA is FSI-exempt under the regulation, and (c) OC linkage means you have to complete it regardless. The 1 km / same ward option is useful when the main plot is in a high-value area where land cost makes it impractical to dedicate ground-floor area to affordable units.

MHADA Allotment Process

Once the developer obtains the Commencement Certificate for the Inclusive Housing component, they must immediately intimate MHADA (Maharashtra Housing and Area Development Authority) regarding the number and details of the affordable tenements.

Here is how the allotment timeline works:

Step Who Timeline What Happens
1. Intimation Developer After CC of IH component Developer informs MHADA about available tenements
2. MHADA processing MHADA 6 months MHADA conducts lottery and forwards allottee list
3. Fallback to Planning Authority Planning Authority Further 6 months If MHADA fails, Planning Authority gets the opportunity
4. Developer disposal Developer After both periods lapse Developer can dispose of units at ASR construction cost + 25%
Under the fallback disposal mechanism, the developer pays 1% of the additional cost (the 25% component) to MHADA as administrative charges.

Pricing under the fallback mechanism

If neither MHADA nor the Planning Authority processes allotment within their respective periods, the developer can sell the units — but not at market rates. The price is capped at the Annual Statement of Rates (ASR) construction cost applicable in the year of disposal/OC, plus 25%. Additionally, the developer must pay 1% of that additional cost to MHADA as an administration charge.

In simple terms: even in the worst case (both authorities fail to act), the developer cannot profit from these units the way they would from market-rate flats. The pricing formula ensures the units remain affordable.

OC Linkage — No OC Without Inclusive Housing

This is the enforcement mechanism that gives Inclusive Housing its teeth. The Occupancy Certificate for the balance (non-affordable) development is linked to the OC for the Inclusive Housing component.

In plain language: you cannot get permission to let people move into your market-rate flats until the affordable flats are also complete and ready. If you build 200 market-rate flats and 40 affordable flats, all 200 families are waiting until those 40 affordable units are done.

This means architects and project managers need to plan the Inclusive Housing component's construction timeline carefully. It is not something you can defer to the end of the project — if it delays, your entire project's handover delays.

Important Exemptions

Not every project on a 4,000+ sq.m. plot requires Inclusive Housing. Regulation 3.8.2 contains specific exemptions. This is one of the most important sections for architects doing feasibility analysis — checking exemptions can fundamentally change a project's financial picture.

Exemption Category Description
Individual bungalow plots Bungalow development irrespective of plot area is exempt
Co-operative society redevelopment Redevelopment of existing co-operative housing society buildings
Government / semi-government projects Specified government, semi-government, and government-controlled projects, including certain BOT/PPP/agency development projects
MHADA colony development Development under MHADA colony regulations
EWS/LIG and PMAY housing Projects that are themselves EWS/LIG developments or under Pradhan Mantri Awas Yojana
Agricultural zone Plots in agriculture or equivalent zone
Public Housing / Housing the Dis-housed Certain Public Housing, Housing the Dis-housed, High Density Housing reservations, and EWS/LIG under other laws
Company/factory staff quarters Qualifying company or factory staff-quarter projects not intended for sale
Accommodation Reservation cases Projects falling under Accommodation Reservation provisions
Already meeting 20% requirement Housing schemes where another applicable regulation or law already requires 20% or more of Basic FSI toward EWS/LIG

Example — Society Redevelopment

A co-operative housing society with 80 members on a 6,000 sq.m. plot decides to redevelop. Despite the plot exceeding 4,000 sq.m., the project is exempt from Inclusive Housing because society redevelopment is specifically excluded. This is one of the most commonly asked questions — and the answer saves significant cost in the project feasibility.

What Changed in the October 2024 GR?

The Government of Maharashtra issued GR Notification No. TPS-1824/1075/CR.87/2024/UD-13, dated 07.10.2024, under Section 37(1AA)(a) of the Maharashtra Regional and Town Planning Act, 1966. This notification sanctioned two specific modifications to Regulation 3.8. The gazette date was fixed as the effective date.

Change 1: Applicability Expanded (Regulation 3.8.1)

Aspect Before (Original UDCPR) After (October 2024 Amendment)
Applicable areas Municipal Corporation areas only All Planning Authority areas in cities/towns with 10 lakh+ population
This is a significant expansion. Projects in non-Municipal Corporation areas that are under a Planning Authority in a 10 lakh+ city now need to check Inclusive Housing applicability where they previously did not.

What this means in practice: if your project is in a Planning Authority area (not a Municipal Corporation) in a city like Pune, Nashik, Nagpur, or any other city with 10 lakh+ population, Inclusive Housing now applies to qualifying plots. Earlier, only projects within the Municipal Corporation limits of these cities were covered.

Change 2: Industrial-to-Residential Conversion — Worker Rehabilitation Proviso (Regulation 3.8.2(b)(iv))

The second change is more specific. It addresses a practical problem: what happens when an old industrial or factory property in a residential zone is being redeveloped, and there are existing factory workers, staff, or tenants living in quarters on that land?

Aspect Before After (October 2024 Amendment)
Terminology "free sale flats" "sale flats" (removed the word "free")
Worker rehabilitation No specific provision New proviso: on industrial-to-residential conversion plots, Inclusive Housing units may be used to rehabilitate existing factory workers, staff, or tenants
Remaining units N/A After rehabilitation, remaining eligible units are offered to MHADA for allotment
Rate cap N/A Rehabilitation units are provided at the rate prescribed under Regulation 3.8.2(b)(iii)

This amendment solves a real problem. Imagine a closed textile mill in central Pune with 50 families of former workers still living in staff quarters on the compound. When the land is converted to residential and a new Group Housing project comes up, the Inclusive Housing units can now be used to rehabilitate those 50 families first. Whatever units remain after rehabilitation go to MHADA for allotment through the normal lottery process.

📋

GR source: Government of Maharashtra, Urban Development Department, Notification No. TPS-1824/1075/CR.87/2024/UD-13, dated 07.10.2024. Signed by Dr. Pratibha Bhadane, Joint Secretary to Government. The notification sanctions modification of UDCPR Regulation 3.8 and fixes the gazette date as the effective date.

What Changed / Is Proposed in August 2026?

The most significant reported change in 2026 is an administrative shift: moving the primary authority for Inclusive Housing possession, management, and allotment from MHADA to the concerned Planning Authority. This was reported in August 2026.

To be clear: the core 20% requirement, the 4,000 sq.m. threshold, the 30–50 sq.m. unit sizes, and the OC linkage mechanism are not reported to have changed. The August 2026 direction is about who administers the Inclusive Housing stock, not how much must be built.

⚠️

Status note: The August 2026 change should be treated as a proposed / pending regulatory transition until the final Official Gazette notification is confirmed. Architects and developers should verify the latest local authority circular before statutory submission. The existing UDCPR text itself already contemplates that the Government may nominate another Authority instead of MHADA if required — so this shift is legally consistent with the existing regulation.

Old vs Proposed New Process — Comparison Table

Issue Existing / Previous Proposed / August 2026 Direction
Primary administrative authority MHADA is the first authority for beneficiary / allottee processing Concerned Planning Authority proposed to become the primary authority for possession, management and allotment
Fallback hierarchy MHADA first; Planning Authority acts if MHADA fails within its period Hierarchy appears intended to become Planning Authority–led rather than MHADA–led
Possession / control of IH stock Existing clauses repeatedly refer to handing over / dealing with MHADA Planning Authority proposed to receive, control and manage the stock locally
Location scrutiny Developer uses the location alternatives allowed by Regulation 3.8.2 Planning Authority reportedly to assess the location and record reasons for its decision
Core 20% quantum 20% requirement as prescribed No verified change to the 20% quantum
4,000 sq.m. trigger 4,000 sq.m. qualifying threshold No verified change to threshold
30–50 sq.m. tenement size Current Group Housing range No verified change identified
1 km / same ward alternative Current alternative-location mechanism Do not treat as deleted; no verified final deletion identified
Pricing formula ASR construction cost +25%, with 1% MHADA admin component No authenticated replacement formula verified
OC linkage Affordable Housing completion/OC affects balance project OC No verified deletion identified

The key takeaway for professionals: 20% of Basic FSI remains the core Group Housing calculation; the 2026 change is mainly about administration and authority, subject to final notification. Do not change your feasibility calculations based on this administrative shift alone.

Why Planning Authorities May Replace MHADA

The existing Regulation 3.8.2 itself already states that the Government may nominate another Authority instead of MHADA if required in future. So a future shift to the concerned Planning Authority is consistent with a power already contemplated by the UDCPR.

The practical logic is straightforward: Planning Authorities are the local bodies that sanction building plans, issue Commencement Certificates, and grant Occupancy Certificates. They already know every project in their jurisdiction. Having them also manage the Inclusive Housing allotment creates a single point of administrative responsibility — rather than the current split where the developer deals with the Planning Authority for approvals but MHADA for affordable housing allotment.

Maharashtra State Housing Policy 2025 — Reform Roadmap

Separate from the UDCPR amendment process, the Maharashtra Government’s Housing Policy 2025 outlines a broader reform roadmap that provides context for the August 2026 administrative direction. The policy is a roadmap — it is not the same as a final operative UDCPR amendment.

Key Policy Directions (Housing Policy 2025)

  • Wider reach: Extending Inclusive Housing coverage beyond the current framework to all Metropolitan Region Development Authority (MRDA) areas.
  • Maha-Awas platform: An AI-enabled / digital platform for housing inventory, applications, and monitoring.
  • Unified data: Integration with a Unified Citizen Data Hub / unified beneficiary-data ecosystem.
  • Digital tracking: Qualifying projects and their Inclusive Housing inventory to be digitally tracked.
  • Faster allotment: A more time-bound digital application and lottery process, replacing the current disconnected workflow.
  • RERA linkage: Better integration of project registration, affordable inventory, and beneficiary agreements with RERA processes.
⚠️

Important: Housing Policy 2025 proposals are not the same as operative UDCPR amendments. Do not treat these policy directions as binding calculation rules. They provide the "why" behind the 2026 administrative change, but the actual operative rules remain as per the current sanctioned UDCPR text and any final Gazette notifications.

📋

Related Recent Amendment (July 2024): A separate Government notice dated 23 July 2024 proposed that where an erstwhile industrial/factory property in a residential zone already has factory workers, staff, or tenants occupying quarters, the Affordable Housing component may be used for rehabilitation of those existing occupants, with remaining units offered to MHADA for allotment. This was subsequently sanctioned via the October 2024 GR described above. This is a separate reform track from the August 2026 administrative direction — do not confuse the two.

Service Quarters Option

The regulation permits up to one-fourth (25%) of the total 20% FSI earmarked for Affordable Housing to be utilised towards construction of Affordable Housing tenements in the form of service quarters, in the same or a separate building. Such service quarters are to be sold only to purchasers of sale flats under the scheme, subject to the prescribed conditions.

In our earlier example with a 2,200 sq.m. Inclusive Housing requirement, up to 550 sq.m. (25% of 2,200) may fall within this service-quarter provision, subject to the above statutory restriction.

Voluntary Inclusive Housing (Regulation 3.8.3)

What if your project is below 4,000 sq.m. or otherwise exempt, but you want to provide affordable housing voluntarily? Regulation 3.8.3 provides an incentive for this.

A developer who voluntarily provides Inclusive Housing where it is not mandatory may receive additional 25% FSI of the land covered under Inclusive Housing on the remaining land, subject to the prescribed prior NOC and conditions under Regulation 3.8.3.

Prospective Applicability — Existing Projects

The Inclusive Housing regulation has prospective-applicability provisions. This means it does not retroactively apply to projects that already held valid Commencement Certificates before the regulation came into effect. However, cases involving revised permissions, additional area applications, or fresh CCs need careful treatment — the specifics depend on the timeline and nature of the revision.

If you are working on a project that had an earlier valid CC and is now seeking a revision or additional area, consult the applicable Planning Authority to determine whether the Inclusive Housing requirement applies to the additional/revised component.

Public Authority Auction Plots (Regulation 3.8.4)

Regulation 3.8.4 deals separately with plots auctioned by public authorities. For future qualifying auctions, the public authority shall stipulate the Inclusive Housing condition wherever applicable. This is a separate track from the general Regulation 3.8.2 applicability and has its own specific provisions.

Inclusive Housing vs Integrated Township Social Housing — They Are Not the Same Rule

A common source of confusion: architects sometimes mix up the Inclusive Housing requirement under Regulation 3.8 with the Social Housing requirement under Integrated Township Projects (ITP) governed by Regulation 14.1.1.9. These are separate regulations with different thresholds, percentages, and mechanisms.

Parameter Inclusive Housing (Reg 3.8) ITP Social Housing (Reg 14.1.1.9)
Trigger Qualifying residential plot ≥ 4,000 sq.m. Integrated Township Project (much larger scale)
Affordable housing quantum 20% of Basic FSI 15% of Residential Basic FSI
EWS share As per allotment (30–50 sq.m. units) 25% of Social Housing FSI
LIG share As per allotment (30–50 sq.m. units) 75% of Social Housing FSI
Rental component Not prescribed One-third of total Social Housing tenements for Rental Housing
Allotment mechanism MHADA lottery → Planning Authority fallback → developer disposal MHADA intimation / lottery process
Price ASR construction cost + 25% ASR construction cost + 25% with administration charge
OC linkage Yes — balance OC linked to IH OC Yes — proportionate linkage
Amalgamation Not permitted Not permitted

The key difference is scale and context. Inclusive Housing (Reg 3.8) applies to individual residential projects on qualifying plots. ITP Social Housing (Reg 14.1.1.9) applies within large-scale Integrated Township Projects that combine residential, commercial, and institutional uses across a much larger area. If you are reading about "15% Social Housing" somewhere, it is almost certainly the ITP rule, not the general Inclusive Housing provision.

What Architects and Developers Should Check Before Feasibility

Before starting a feasibility study for any residential project in Maharashtra, run through this checklist:

  1. Is the qualifying plot area 4,000 sq.m. or more after prescribed deductions (DP road, reservations)?
  2. Is the project in an applicable area? After October 2024: all Planning Authority areas in 10 lakh+ population cities.
  3. Does any exemption apply? Check society redevelopment, bungalow plots, government projects, agricultural zone, PMAY, etc.
  4. Calculate 20% of Basic FSI — not total FSI, not Premium, not TDR.
  5. Plan the affordable units within 30–50 sq.m. carpet area each.
  6. Factor OC linkage into the construction timeline — the IH component must be ready before the balance project can get OC.
  7. Decide on same-plot vs alternate location — if alternate, ensure it is within 1 km or same ward.
  8. Account for the FSI-exempt / over-and-above IH BUA in your area statement — IH area is over and above permissible FSI under Regulation 3.8.2.
  9. Check for industrial-to-residential conversion — if applicable, the October 2024 worker rehabilitation proviso may apply.
  10. Check the August 2026 status — verify whether the Planning Authority (not MHADA) is now the primary allotment authority in your jurisdiction. This is a proposed transition; confirm the latest circular.
  11. Verify with the local Planning Authority — regulations are subject to local interpretation, circulars, and amendments.

Check Inclusive Housing Applicability for Your Plot

Checking whether Inclusive Housing applies to your plot is only one part of project feasibility. FSI Atlas helps architects and real-estate professionals evaluate permissible FSI, TDR, development controls, parking, market inputs and project feasibility in one workflow.

Open FSI Atlas → Browse Knowledge Base

Frequently Asked Questions

What is Inclusive Housing under UDCPR Regulation 3.8?

Inclusive Housing is a mandatory provision that requires developers to build affordable EWS (Economically Weaker Section) and LIG (Low Income Group) housing as part of qualifying residential projects on plots of 4,000 sq.m. or more. The developer must construct tenements equal to at least 20% of the Basic FSI, with unit sizes between 30 and 50 sq.m. carpet area. These units are allotted through MHADA's lottery system, not sold at market rates.

Is Inclusive Housing mandatory for all plots above 4,000 sq.m. in Maharashtra?

Not automatically. While 4,000 sq.m. is the primary trigger, the regulation contains several exemptions — including individual bungalow plots, redevelopment of existing cooperative housing societies, certain government projects, MHADA colony development, PMAY housing, and plots in agricultural zones. Always check the specific exemptions under Regulation 3.8.2 before concluding that Inclusive Housing applies.

How is the 20% Inclusive Housing calculated — on Basic FSI or total FSI?

On Basic FSI only. Premium FSI, TDR, and any other additional permissible FSI do not attract a separate or additional Inclusive Housing obligation. For example, if your plot is 10,000 sq.m. and Basic FSI is 1.10, the IH requirement is 20% of 11,000 sq.m. = 2,200 sq.m. — even if total project FSI reaches 3.0 through premiums and TDR.

Can Inclusive Housing be provided on another plot within 1 km?

Yes. Regulation 3.8.2 permits the affordable housing component to be provided at another location within 1 km of the original plot or within the same ward, subject to prescribed conditions. For Group Housing on an alternate plot, the regulation includes a 40% of basic permissible FSI receiving-plot mechanism with land-rate proportional adjustment.

Who allots Inclusive Housing units — MHADA or the Planning Authority?

Under the existing framework, MHADA is the primary authority. After the developer obtains the Commencement Certificate and intimates MHADA, MHADA has 6 months to process allottees through its lottery system. If MHADA fails within this period, the concerned Planning Authority gets a further 6 months. If that also fails, the developer can dispose of the units at ASR construction cost + 25%.

What changed in the October 2024 Inclusive Housing GR?

Two confirmed changes: (1) Applicability expanded from only Municipal Corporation areas to all Planning Authority areas in cities with 10 lakh or more population. (2) A new proviso was added allowing Inclusive Housing units on industrial-to-residential conversion plots to be used for rehabilitation of existing factory workers, staff, or tenants, with remaining units offered to MHADA for allotment at the prescribed rate.

What changed in Maharashtra Inclusive Housing rules in August 2026?

The main reported August 2026 regulatory direction is a shift from the existing MHADA-centric administrative model toward a Planning-Authority-centric model. The concerned Planning Authority is proposed to become the primary authority for possession, management, and allotment of Inclusive Housing stock. The core 20% requirement, 4,000 sq.m. threshold, and unit size rules are not reported to have changed. Treat this as a proposed / pending transition until the final Official Gazette notification is confirmed.

Has MHADA been removed from Inclusive Housing in 2026?

Not definitively. The August 2026 direction proposes shifting primary responsibility from MHADA to the concerned Planning Authority, but this should not be treated as a confirmed repeal of MHADA’s role unless the final Official Gazette notification explicitly says so. The existing UDCPR text already contemplates that the Government may nominate another Authority instead of MHADA. Verify the latest position with your local Planning Authority before submission.

Does the new 2026 Inclusive Housing proposal apply to PMC and PCMC?

The August 2026 administrative direction, if confirmed by final Gazette notification, would apply to all applicable Planning Authority areas — which would include PMC (Pune Municipal Corporation) and PCMC (Pimpri-Chinchwad Municipal Corporation) areas since they already meet the 10 lakh+ population criterion under the October 2024 amendment. Verify the latest local authority circular for confirmation.

What is Maharashtra Housing Policy 2025 proposing for Inclusive Housing?

The Housing Policy 2025 outlines a broader reform roadmap: extending Inclusive Housing to all MRDA areas, a digital Maha-Awas platform for housing inventory and monitoring, integration with a Unified Citizen Data Hub, digital project tracking, time-bound digital allotment processes, and RERA integration. These are policy directions — not operative UDCPR amendments — and provide the context for the August 2026 administrative change.

Is Inclusive Housing applicable to society redevelopment?

No. Redevelopment of existing co-operative housing society buildings is specifically exempted under Regulation 3.8.2. This is one of the most commonly asked questions — the exemption exists because society redevelopment already addresses the housing needs of existing members.

Can the balance project get OC before the Inclusive Housing component is complete?

No. The OC for the balance (non-affordable) development is linked to the OC for the Inclusive Housing component. The balance development cannot receive its Occupancy Certificate until the required OC for the Affordable Housing component is issued. This is the primary enforcement mechanism for Inclusive Housing compliance.

Can Inclusive Housing units be amalgamated into larger flats?

No. Inclusive Housing plots and tenements cannot be amalgamated. Each unit must remain a separate, independent dwelling within the prescribed 30–50 sq.m. carpet area range. This prevents the affordable stock from being converted into larger market-rate units.

Can part of the Inclusive Housing component be used as service quarters?

Yes. Up to one-fourth (25%) of the total 20% FSI earmarked for Affordable Housing may be utilised for Affordable Housing tenements in the form of service quarters, subject to prescribed conditions. Such service quarters are to be sold only to purchasers of sale flats under the scheme.

What is the difference between Inclusive Housing (Reg 3.8) and ITP Social Housing?

They are separate regulations. Inclusive Housing (Reg 3.8) requires 20% of Basic FSI on qualifying plots of 4,000 sq.m. or more. ITP Social Housing (Reg 14.1.1.9) requires 15% of Residential Basic FSI within Integrated Township Projects, with 25% for EWS, 75% for LIG, and one-third of total Social Housing for rental housing. The triggers, thresholds, and mechanisms are different.

Does Premium FSI or TDR attract an additional Inclusive Housing requirement?

No. The 20% requirement is calculated only on Basic FSI. Premium FSI, TDR, or any other additional permissible FSI does not attract a separate or additional Inclusive Housing obligation. This is one of the most important points for project feasibility calculations.

AM

Ar. Anup Mahajan

Founder, FSI Atlas

Anup is a practising architect and the founder of FSI Atlas — an online platform that helps architects, developers and real-estate professionals evaluate FSI, TDR, development controls and project feasibility across Maharashtra.

Disclaimer

This article is for informational purposes only and does not constitute legal advice. Development regulations are subject to amendments, authority-specific interpretation, and current government notifications. Always verify the latest sanctioned regulation, applicable GRs, and local authority circulars before making statutory submissions or investment decisions. Last updated: September 2026.